Over 80 years of experience in structural stabilization and foundation work, including engineering and contractor services related to drilling and grouting, anchor and tieback systems, installation of instrumentation, and cellular concrete and fly ash placement.

 

Services

Mine Subsidence

Services >> Mine Subsidence >> Wabash Valley

Wabash Valley Correctional Institute, Indiana

The State of Indiana was expanding the Wabash Valley Correctional Institute over an area of abondoned coal mines. The depth to the roof of the mine was 300 feet. The mine was completely flooded, the water table only 15 feet below the surface.

Significant engineering work had been performed to delineate the mine and remaining supports. The work involved the utilization of mine maps, core drilling and ground penetrating radar. Three weak areas were discovered where the existing pillar spacing created a potential for subsidence at the surface.

It was decided to stabilize the mine by drilling into the mine and creating barriers with a lower slump grout at natural openings. The voids would then be completely filled with a high slump infill grout.

The schedule for performing the work was very tight. Funding of the job was contingent on phases being complete on a compacted schedule. The State of Indiana wanted the building contractor to be able to use the entire construction season for surface construction. This required the subsidence contractor to work multiple shifts to mantain the schedule.

SOLUTION

The Judy Company, Inc. was issued a contract for just over $1.6 million to complete the subsidence remediation. The contract allowed 90 days for completion of the project and included a $15,000 bonus for early completion. By working multiple shifts, just over 60 calendar days were needed for substantial completion.

Venture Drilling (Talequah, OK) was issued a subcontract for the drilling. Using an air rotary system, 31,102 lf of drilling was performed. A Drilltech D-40-K was modified by installing two hydraulic pipe racks holding 300+ feet of pipe. A 3" pipe was then fitted to the bottom of the hole for grout injection.

A continuous mix grout plant was mobilized to produce the majority of the fill. Conventional concrete pumps were used to place the grout. A magnetic flow meter with a strip chart recorded monitored flow and pressure during placement. The mine was significantly more rubbelized than anticipated and mixed designs were modified to maximize penetration. The grout mix utilized high percentages of Class "C" flyash and local river sand. When the job was finally complete, over 9,000 cu. yds. of fill had been placed.

Continuous Mix Grout Plant-Supplies Material at a Steady Rate.

Injection Pipe Withdrawn as Void Was Filled

MINE SUBSIDENCE APPLICATIONS

Rock Springs, Wyoming
stabilization of neighborhood developed overtop of a coal mine

Island Creek Coal Company
stabilization of coal production tower overtop mine

Wabash Valley Correctional Institute
preparation of flooded mine prior to expansion of correction facility