Over 80 years of experience in structural stabilization and foundation work, including engineering and contractor services related to drilling and grouting, anchor and tieback systems, installation of instrumentation, and cellular concrete and fly ash placement.

 

Services

Anchoring

Services >> Anchoring >> Fort Smith

Fort Smith Lock and Dam

Installation of sheetpile tiebacks, counterfort anchors and rock face anchors, Lock and Dam 13-Hydopower Project, Fort Smith, Arkansas.

ANCHORING APPLICATIONS

Cooper River
Tendon installation at Cooper River, Charleston, S.C. Tendons were post tensioned to 880 kips to anchor bridge piers in harbor.

Arrowhead and Kauffman Sports Stadiums, Kansas City
Rock bolt installation and foundation stabilization, Jackson County Sports Complex, Kansas City, MO.

New Savannah Bluff Lock and Dam
Rock anchor installation, New Savannah Bluff Lock and Dam, Augusta, GA.

Fort Smith Lock and Dam
Installation of sheetpile tiebacks, counterfort anchors and rock face anchors, Lock and Dam 13-Hydopower Project, Fort Smith, Arkansas.

Lock and Dam 13
At Lock and Dam 13, on the Arkansas River, 3800 tiebacks and rock anchors were installed at a cost of $1,250,000.

Bagnell Dam
The Judy Company developed tie downs for Bagnell Dam at the Lake of the Ozarks which produced over 1.5 million pounds of force.

Olmos Dam
At Olmos Dam in San Antonio, Texas, The Judy Company installed anchors to prevent dam failure by overtopping. Overtopping did actually occur since installation.