Springfield Underground PDF Print E-mail

Project:

Springfield Underground

 

Location:

Springfield MO

 

Owner:

Springfield Underground, Inc.


General:

The Judy Company

 

Description:

400,000 sq.ft or underground warehouse, ≈ 16,000 roof bolts, 6’ and 8’ long, resin grouted. Roof of mine was 40 feet high. Specialty equipment and procedures were required. Crews worked 20 hrs per day to meet the customers’ schedule. The additional work was in mine areas and tunnels, the work was roof bolting 6’, 8’, 12’ and 15’ resin grouted bolts and 25’ mechanically anchored, fully grouted bolts.