Over 80 years of experience in structural stabilization and foundation work, including engineering and contractor services related to drilling and grouting, anchor and tieback systems, installation of instrumentation, and cellular concrete and fly ash placement.

 

Engineer's Corner

Specifications - Compaction Grouting

PART I - GENERAL

Scope:

This section covers compaction with Sand/Cement/Flyash grout including the installation of injection pipes.

General:

The responsibilities of the Contractor include project control, supervision, labor, materials and equipment to accomplish the following items of work:

  • Submit a detailed grouting plan to the Owner or Owners representative for review prior to beginning of work.

  • Install Grout Pipes

  • Monitor ground and existing structure movements during grouting operations.

  • Perform grouting program under the supervision of personnel experienced in grouting for settlement control.

Quality Control:

Quality control shall be the responsibility of the grouting Contractor. Due to the specialized nature of the grouting operation required to perform the specified stabilization, proposals will only be accepted from pre-qualified grouting Contractors. To apply for pre-qualification, the grouting Contractor shall submit a list of compaction grouting projects undertaken in the past five years. At least three of the grouting projects specified shall be of equivalent difficulty and/or scope. No Contractor will be considered acceptable without a minimum of five years experience in compaction grouting.

Cylinders must be taken by the Contractor daily or when the mix design changes. Cylinders shall be 3" x 6". Three cylinders shall be taken and marked with the date and time of day taken. Cylinders shall be broken at 7 and 28 days with the remaining cylinder being held. A testing laboratory certified by the Owner shall test cylinders.

The work plan must be submitted to the Owner for review and comments a minimum of 5 calendar days prior to commencement of work in the field. The work-plan shall contain the following:

  • The proposed mix design.

  • Hole layout and spacing

  • System used to monitor movement of surface or structures.

  • Estimate of the duration of the work time in the field.

  • Grout pump manufacturer, model number and pressure capacities.

  • Refusal criteria.

The intent of the grouting is to produce a 15% improvement in the density of the base material within the limits shown on the drawing.

The location of the compaction grouting is shown on the drawings.

The subsurface investigation report and soil samples obtained during the subsurface investigation may be examined by contacting the Owner, a minimum of two days in advance of the day of examination.

Part 2- PRODUCTS

Equipment:

The equipment used to mix and pump grout shall be specifically designed for this purposed. Because of the high pressure involved all equipment, including hoses, couplings, gauges and pipes, shall be able to operate to the maximum requirements stated in these specifications. The mixing and grout pump system shall be designed to provide continuous flow of the grout mixture without interruption during any single hookup for a specific stage due to inadequate batching or pump feed capacity.

Grout mixing system: The grout mixing system shall be capable of thoroughly mixing grout over the specified range. Grout shall either be supplied by transit mix or mixed on site. For each batch of transit mixed grout, a ticket shall be issued by the mix plant stating the amount of Sand, Cement, Flyash, Water any additives, the time mixed, amount of water added at the site, time the truck has fully discharged. Any grout over 3 hours old shall be wasted unless it can be demonstrated that extended hold time has no detrimental effect. On site mixing systems shall be capable of precisely measuring, recording, and mixing all materials.

Grout Pump System: The grout pump shall include a positive displacement type pump with variable speed capabilities. The grout pump shall have the capability of injecting grout at a pressure of 800 psi. The pump shall have a minimum capacity of .05 cfm and maximum of up to 5 cfm. Pumps shall be equipped with remote controls for operation in vicinity of the probe collar to control the injection process.

Grout Delivery System. The grout delivery system shall consist of hoses, couplings, and pipes compatible with the equipment used for this work and shall be capable of withstanding the pressures delivered by the pump. Pressure gauges shall be provided at the pump discharge and at the top of the injection pipe to monitor pressure.

Pressure Gauges. All pressure gauges shall be adequately protected form the grout with suitable gauge savers to provide accurate pressure reading on a continuous basis and shall be calibrated to a Master Gauge prior to use.

Grout Injection Volume measurement System. There shall be a reliable mechanical means of measuring the quantity of grout pumped in every stage to within 0.25 cf.

Materials:

Sand: Sand shall conform to ASTM C-33

Cement. Cement (if used) shall be Type I or Type II Portland and free of contamination. Cement shall be either supplied in water resistant paper bags or in bulk. Cement containing lumps shall be rejected or screened to remove lumps.

Flyash. Flyash (if used) shall conform to ASTM C-618 and be either Class C or Class F.

Lime. Lime (if used) shall be hydrated agricultural lime. Lime shall be supplied in water resistant paper bags or in bulk. Lime containing lumps shall be rejected or screened to remove lumps.

Water. Water shall be clean and free from contamination. Volume shall be as necessary to achieve the desired slump.

Admixtures. Admixtures such as a superplastizer or a pumping aid may be added to increase set time or improve pumpability.

 

PART 3 - EXECUTION

Grout Pipe Installation:

The grout pipes shall be installed utilizing the primary and secondary sequence. The adjacent primary grout pipes shall be grouted prior to installing or injection into the secondary pipes. The Secondary pipes shall be used to verify the densification of the soil strata.

The pipes shall be either drilled or driven. The end of the pipe must be sealed to prevent strata from entering the pipe during installation. The injection pipes shall be installed to prevent grout leakage and/or premature upward movement of the casing during injection of high-pressure compaction grout.

Pipes shall be steel of sufficient diameter and wall thickness to allow the grout to be placed over the range of slumps and to the pressures as specified.

Grout Injection:

Grout shall be mixed on site or provided from a transit mix grout truck. The slump of the mix shall not exceed 3 inches. Grout shall be injected at a rate not to exceed 4.0 cfm unless authorized by the Owner.

Grouting pressure shall be continuously monitored at the surface connection to the injection pipe with a suitable protected gauge. A grid pattern for primary injection pipes shall be established and the grout shall be injected beginning at the lower depth of the grouting limits as shown on the plans.

The grouting process shall progress in stages within each injection pipe using the bottom up method. The bottom up method stages start at the bottom of the grouting pipe, at least 1 ft into the underlying dense material, progressing upward at 2 ft maximum intervals. The ground surface and adjacent structures shall be monitored at all times during grout injection for surface movement (heave). Pre-established monitor points on any structure shall be monitored during grout injection.. Grout injection shall cease for any given stage when movement is detected or when maximum injection pressure is reached or when a sudden drop in pressure is noted. Pressure shall drop when the injection pipe is raised or the pipe will be considered plugged and shall be removed and reinstalled or cleaned out by a wash hose from the surface.

After completion of primary grouting, a secondary grid pattern, split spacing the first grid pattern injection points, shall be established. Grouting in secondary holes shall proceed as described for primary holes. Quantities for the secondary stage shall be compared with grout injected during the primary stage to ensure the subsurface material is becoming densified. The Owner shall be notified of the quantities placed in the secondary holes before further split spacing or an area is determined complete.

The compaction grout pumping rates and pressures shall be carefully controlled.

Any hole lost due to Contractor negligence or error shall be replaced at not charge to the Owner.

Testing and Quality Control. The Contractor shall pay the cost of sampling and testing.

All daily drilling, grouting and testing reports shall be submitted to the Owner within 24 hours. A level control system will be installed and operated by the Contractor for use during grouting. Changes in elevation of the control points shall be tabulated and submitted to Owner at the completion of the project.

Drilling reports shall contain at least the following information: Name of driller, type of drill, method used, date, location of hole, tip depth or elevation of injection pipe.

Grouting reports shall contain at least the following information: Name of grouting technician, grout mix, quantity injected per stage, date, rate of pumping, beginning and final pressure obtained in each stage. The reason for refusal, such as refusal pressure, movement of the surface, movement of a structure.

Protection or Work Area and Cleanup:

During the work operations the Contractor shall take such precautions as may be necessary to permit drill cuttings, equipment exhaust, oil, wash water and grout from defacing and/or damaging the surrounding area.

The Contractor shall furnish such pumps as may be necessary to care for wastewater and grout from his operations and shall clean up all waste resulting from his operations.

Measurement and Payment:

Mobilization/Demobilization will be measured as lump sum. Eighty percent will be paid when all equipment is on site. The remaining twenty percent will be paid after all equipment is removed from site, the site is restored, and all reports, including drilling, grouting, and elevations, are received by the Owner.

Injection pipes shall be measured by each pipe installed to the depth indicated on the Plans. Payment will be made for each pipe successfully installed. Pipes that become plugged shall be removed and replaced at no charge to the Owner.

Grout shall be measured by the Cubic Yard successfully placed. Grout shall be paid for by the Cubic Yard successfully placed.

Grout wasted at the direction of the Owner as a result of grout hole refusal will be paid at the cost specified. Measurement and payment will be made by the cubic yard.

Item #

Item Unit

Mobilization

ls

Injection Pipes Installed

ea

Grout Placed

cy

Grout Wasted

cy