DOTs Warm Up
to New Technology
click here for the Better Roads Article
Adobe PDF Download Version
Soil and rock nailing is a relatively new
construction technique first used in Europe to stabilize and construct
tunnels. In North America, it is quickly becoming a popular method of
soil and rock retention, slope stabilization, and shoring.
Soil nailing provides project owners and
departments of transportation economic benefits and a rapid means of
retaining wall and retention support system construction. Two very
different projects proved the advantages of soil nailing over
conventional retaining wall construction for DOTs in Kentucky and Iowa.
Ken
Abud, business development manager for The
Judy Company, Kansas City, says that soil nailing projects generally
follow the same basic procedure. Geotechnical engineers design the soil
nailing project, taking into account soil compatibility and strength
requirements of the grout and shotcrete. The technique, appropriate in
many cohesive soils of fragmented rock, is top-down construction.
A bench is excavated ranging between 4 and 6 feet
in height. Holes are drilled into the excavated face typically measuring
6 to 8 inches in diameter in soil and 3 to 4 inches in rock. Typically
holes are angled at 15 degrees below horizontal. The hole is pumped full
of ready-mixed grout soon after drilling to ensure the hole remains
open. Nails, generally continuously threaded steel bars, are long enough
to penetrate the failure plane of the excavation, and are inserted
immediately following grouting. The nails are equipped with centralizers
to ensure central placement in the grouted hole. The concept is to
stabilize the soil by creating a grouted mass that the surrounding soil
will act upon in friction. The grout also provides corrosion protection
for the nail. Once the grout sets, the protruding nails are fitted with
a steel plate to transfer forces from the wall to the nail. Horizontal
and vertical drain strips are then installed onto the facing to control
seepage and eliminate hydrostatic pressure buildup.
Reinforcing steel is applied and the face is
shotcreted. For temporary walls, as in shoring or behind a cast-in-place
concrete finish, the surface can be left rough or lightly troweled. For
permanent walls, the shotcrete can be hand troweled or even sculptured
and stained to blend into the natural surroundings depending on the
desired look.
Because of the potential that the soil will
collapse after being excavated, a soil nailing contractor only cuts as
long a bench as crews can complete in a 24 hour period. “You cut only
what can be finished in a day, shotcrete and everything,” Abud says.
“On any given job, the pump is almost continually working, so it must
be reliable. It is the key to making the technique work, maintaining
productivity, and staying on schedule and budget.”
ON
SITE
Soil nailing has several applications, and the
Judy Company has been contracted for a range of projects across
the nation. The company recently completed an 8,500-square foot
wall in Pike county, Kentucky as a subcontractor. The original
plans required a cast-in-place wall in front of the shotcrete
shoring. As an alternative, the company proposed a soilnailed
and shotcreted wall sculpted and stained to look like adjacent
highway cuts. The proposal was accepted and Boulderscape,
Capistrano Beach, California was contracted to place and sculpt
the shotcrete..
Working from a manlift, the shotcrete was placed
with a Schwing concrete pump. Sculptors from another manlift
carved the shotcrete from the top down using hand trowels and
brushes, emulating natural rock formations in the area. After
curing, the wall was stained, making the finished product look
like a natural cut.
At the same time, the contractor was finishing a
massive, 63,000-square foot soil nailing project on I-235 in Des
Moines as specified by the Iowa DOT.
Crews finished over 1,500 square feet a day.
Judy Company President Pat Carr says the Des
Moines project is a true testimony to soil nailing as a
successful soil retention technique. “Using top-down
construction and this technology, the highway could be
constructed in the minimum right-of-way. Soil nailing allowed
excavation very close to city streets and utilities and
eliminated detours during construction,” he says.
(by Sara McGray, SAGA representative in
Minneapolis.)